98230 | Tabor Road over Tacony Creek (Bridge) (Philadelphia City)
This project is a bridge rehabilitation/replacement of Tabor Road over Tacony Creek in the City of Philadelphia.
The bridge carrying Tabor Road over Tacony Creek is a three span, non-composite, adjacent box beam bridge that was built in 1957. Anticipated work includes demolition and replacement of the superstructure; rehabilitation of the existing reinforced concrete abutments, wingwalls, and piers; full depth pavement reconstruction of the bridge approaches; replacement of the parapet, railing, curb and sidewalk; reconstruction of ADA curb ramps; coordinated relocation of utility facilities; and other miscellaneous construction. Construction will be staged, allowing the bridge to remain open for traffic and avoiding the need for a lengthy detour. Temporary pedestrian and multi-use trail detours may be required.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This project is a component of the County Bridge Line Item (MPMS #95447).
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 183 | $328 | $0 | $0 | $0 | $0 |
FD | LOC | $82 | $0 | $0 | $0 | $0 |
UTL | LOC | $0 | $20 | $100 | $0 | $0 |
UTL | 183 | $0 | $80 | $396 | $0 | $0 |
CON | STU | $0 | $3482 | $1000 | $5964 | $0 |
CON | LOC | $0 | $217 | $62 | $372 | $0 |
CON | 183 | $0 | $652 | $187 | $1118 | $0 |
Program Year Totals: | $410 | $4,451 | $1,745 | $7,454 | ||
Total FY23-FY26 Cost: | $14,060 | Total FY23-FY34 Cost: | $14,060 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Start of Phase | 2017-02-10 |
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
CON | Award Contract | 2022-09-21 |
FD | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2022-10-15 |
CON | Start of Phase | 2022-10-19 |
CON | Notice to Proceed | 2022-10-19 |
FD | Completion of Phase | 2022-10-19 |
FD | PS+E to District Contract Management | 2023-12-15 |
CON | Let | 2024-04-25 |
CON | Physical Work Complete | 2025-11-28 |
CON | Completion of Phase | 2026-10-31 |
CON | Project Agreement End Date | 2027-05-29 |