This project is a bridge rehabilitation/replacement of Tabor Road over Tacony Creek in the City of Philadelphia.
The bridge carrying Tabor Road over Tacony Creek is a three span, non-composite, adjacent box beam bridge that was built in 1957. Anticipated work includes demolition and replacement of the superstructure; rehabilitation of the existing reinforced concrete abutments, wingwalls, and piers; full depth pavement reconstruction of the bridge approaches; replacement of the parapet, railing, curb and sidewalk; reconstruction of ADA curb ramps; coordinated relocation of utility facilities; and other miscellaneous construction. Construction will be staged, allowing the bridge to remain open for traffic and avoiding the need for a lengthy detour. Temporary pedestrian and multi-use trail detours may be required.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This project is a component of the County Bridge Line Item (MPMS #95447).

Limits: Tabor Road over Tacony Creek
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FD183$328$0$0$0$0
FDLOC$82$0$0$0$0
UTLLOC$0$20$100$0$0
UTL183$0$80$396$0$0
CONSTU$0$3482$1000$5964$0
CONLOC$0$217$62$372$0
CON183$0$652$187$1118$0
Program Year Totals:$410$4,451$1,745$7,454 
Total FY23-FY26 Cost:$14,060Total FY23-FY34 Cost:$14,060 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDStart of Phase2017-02-10
FDPhase Approved by PMC
UTLPhase Approved by PMC
CONPhase Approved by PMC
CONAward Contract2022-09-21
FDPhase on Approved STIP
UTLPhase on Approved STIP
CONPhase on Approved STIP
UTLPlan to Utility Unit2022-10-15
CONStart of Phase2022-10-19
CONNotice to Proceed2022-10-19
FDCompletion of Phase2022-10-19
FDPS+E to District Contract Management2023-12-15
CONLet2024-04-25
CONPhysical Work Complete2025-11-28
CONCompletion of Phase2026-10-31
CONProject Agreement End Date2027-05-29