98229 | 59th Street over AMTRAK (Bridge) (Philadelphia City)

This project is a bridge replacement of 59th Street over AMTRAK in the City of Philadelpia.
The current structure was built in 1926, and consists of a four simple-span, partially concrete-encased-steel girder/floorbeam/jackarch superstructure atop reinforced concrete abutment and pier substructures. The anticipated work includes demolition and removal of the existing superstructure and portions of the existing reinforced concrete abutments & piers and construction of a new steel multi-girder bridge with reinforced concrete composite deck atop reinforced concrete abutments and piers; as well as roadway approach reconstruction and repaving, curb and sidewalk reconstruction, streetlighting improvements, ADA accessibility improvements, railroad electric traction (ET) system modification and utility relocations, and other related work.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This project is a component of the County Bridge Line Item (MPMS #95447).

Limits: 59th Street over AMTRAK
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FDLOC$212$0$0$0$0
FD183$849$0$0$0$0
UTL183$0$1614$1328$3238$0
UTLLOC$0$403$332$809$0
CON183$0$0$1567$2943$1326
CONLOC$0$0$522$981$441
CONBOF$0$0$8355$15696$7076
Program Year Totals:$1,061$2,017$12,104$23,667 
Total FY23-FY26 Cost:$38,849Total FY23-FY34 Cost:$47,692 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
CONPhase Approved by PMC
UTLPhase Approved by PMC
UTLStart of Phase2021-06-17
UTLCompletion of Phase2021-12-30
FDPhase on Approved STIP
CONPhase on Approved STIP
UTLPhase on Approved STIP
FDStart of Phase2023-03-17
UTLPlan to Utility Unit2023-05-05
FDPS+E to District Contract Management2024-06-15
CONLet2025-04-24
CONAward Contract2025-05-24
FDCompletion of Phase2025-06-23
CONStart of Phase2025-06-23
CONNotice to Proceed2025-06-23
CONPhysical Work Complete2026-06-25
CONCompletion of Phase2026-08-24
CONProject Agreement End Date2027-12-24