98221 | Strock's Grove Road over Beaver Creek (CB# 333) (Nockamixon Township, Bucks County)
This project is a bridge rehabilitation of Stock's Grove Road over Beaver Creek in Nockamixon Township, Bucks County.
Funding for this project will be drawn down from the County Bridge Line Item (MPMS #95447) at the appropriate time.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or
state Categorical Exclusion clearance.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | LOC | $230 | $50 | $0 | $0 | $0 |
CON | 183 | $920 | $200 | $0 | $0 | $0 |
Program Year Totals: | $1,150 | $250 | $0 | $0 | ||
Total FY23-FY26 Cost: | $1,400 | Total FY23-FY34 Cost: | $1,400 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Final Utility Clearance | |
CON | Final ROW Clearance | |
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Let | 2023-06-08 |
CON | Award Contract | 2023-07-08 |
CON | Start of Phase | 2023-08-21 |
CON | Notice to Proceed | 2023-09-05 |
CON | Physical Work Complete | 2024-06-21 |
CON | Completion of Phase | 2024-08-20 |
CON | Project Agreement End Date | 2025-12-20 |