98042 | Conestoga Rd o/ Pickering (West Pikeland Township, Chester County)
This project will include the replacement of the bridge spanning Conestoga Road over branch of Pickering Creek.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 185 | $141 | $0 | $0 | $0 | $0 |
ROW | 185 | $84 | $0 | $0 | $0 | $0 |
UTL | 185 | $56 | $0 | $0 | $0 | $0 |
CON | STU | $0 | $1476 | $0 | $0 | $0 |
CON | 185 | $0 | $369 | $0 | $0 | $0 |
Program Year Totals: | $281 | $1,845 | $0 | $0 | ||
Total FY23-FY26 Cost: | $2,126 | Total FY23-FY34 Cost: | $2,126 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Start of Phase | 2013-07-12 |
ROW | Start of Phase | 2013-07-12 |
ROW | Completion of Phase | 2014-07-11 |
UTL | Completion of Phase | 2014-07-11 |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2023-07-20 |
ROW | Plan to ROW Unit | 2023-07-20 |
FD | Start of Phase | 2023-08-19 |
CON | Notice to Proceed | 2024-04-29 |
CON | Start of Phase | 2024-04-29 |
FD | Completion of Phase | 2024-04-29 |
FD | PS+E to District Contract Management | 2024-05-20 |
CON | Let | 2024-08-22 |
CON | Award Contract | 2024-09-21 |
CON | Physical Work Complete | 2025-11-09 |
CON | Project Agreement End Date | 2027-05-10 |
CON | Completion of Phase | 2028-03-30 |