98039 | Ship Road over Valley Creek (Bridge) (West Whiteland Township, Chester County)
This project will include the removal and replacement of an existing poor condition bridge along Ship Road in West Whiteland Township, Chester County.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 185 | $150 | $0 | $0 | $0 | $0 |
ROW | 185 | $92 | $0 | $0 | $0 | $0 |
UTL | 185 | $12 | $0 | $0 | $0 | $0 |
UTL | STP | $50 | $0 | $0 | $0 | $0 |
CON | 185 | $0 | $0 | $871 | $100 | $462 |
Program Year Totals: | $304 | $0 | $871 | $100 | ||
Total FY23-FY26 Cost: | $1,275 | Total FY23-FY34 Cost: | $1,737 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Start of Phase | 2018-02-15 |
ROW | Completion of Phase | 2019-02-14 |
FD | Completion of Phase | 2019-02-14 |
UTL | Completion of Phase | 2019-02-14 |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2023-03-30 |
UTL | Plan to Utility Unit | 2023-08-28 |
ROW | Plan to ROW Unit | 2023-08-28 |
CON | Start of Phase | 2024-04-29 |
CON | Notice to Proceed | 2024-04-29 |
FD | PS+E to District Contract Management | 2024-05-29 |
CON | Let | 2024-08-22 |
CON | Award Contract | 2024-09-21 |
CON | Physical Work Complete | 2025-05-30 |
CON | Completion of Phase | 2025-07-29 |
CON | Project Agreement End Date | 2026-11-28 |