98037 | Niantic Road over Perkiomen Creek (Bridge) (Douglass Township, Montgomery County)
This project will include the removal and replacement of an existing poor condition Bridge.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 185 | $0 | $174 | $0 | $0 | $0 |
ROW | 185 | $0 | $93 | $0 | $0 | $0 |
UTL | 185 | $0 | $0 | $0 | $26 | $0 |
CON | 185 | $0 | $0 | $0 | $0 | $1851 |
Program Year Totals: | $0 | $267 | $0 | $26 | ||
Total FY23-FY26 Cost: | $293 | Total FY23-FY34 Cost: | $2,144 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
UTL | Start of Phase | 2018-03-01 |
ROW | Start of Phase | 2018-03-01 |
FD | Completion of Phase | 2019-01-31 |
UTL | Completion of Phase | 2019-01-31 |
ROW | Completion of Phase | 2019-01-31 |
UTL | Plan to Utility Unit | 2022-06-20 |
FD | Start of Phase | 2022-06-30 |
ROW | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-05-31 |
FD | PS+E to District Contract Management | 2023-09-03 |
CON | Notice to Proceed | 2023-09-11 |
CON | Start of Phase | 2023-09-11 |
CON | Let | 2023-12-07 |
CON | Award Contract | 2024-01-06 |
CON | Completion of Phase | 2024-06-04 |
CON | Physical Work Complete | 2024-12-02 |
CON | Project Agreement End Date | 2026-06-02 |