98035 | Water Works Road over Rock Run (West Caln Township, Chester County)
This project involves rehabilitating or replacing the Bridge at Water Works Road over Rock Run. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | BOF | $250 | $0 | $0 | $0 | $0 |
PE | TOLL | $0 | $0 | $0 | $0 | $0 |
ROW | BOF | $0 | $0 | $0 | $0 | $93 |
ROW | 185 | $0 | $0 | $0 | $0 | $23 |
UTL | BOF | $0 | $0 | $0 | $0 | $64 |
UTL | 185 | $0 | $0 | $0 | $0 | $16 |
CON | 185 | $0 | $0 | $0 | $0 | $334 |
CON | BOF | $0 | $0 | $0 | $0 | $1332 |
Program Year Totals: | $250 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $250 | Total FY23-FY34 Cost: | $2,112 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
PE | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
PE | Start of Phase | 2022-10-01 |
ROW | Plan to ROW Unit | 2024-10-15 |
PE | N. E. P. A. Approval | 2024-10-15 |
UTL | Plan to Utility Unit | 2024-10-15 |
UTL | Start of Phase | 2024-10-15 |
ROW | Start of Phase | 2024-10-15 |
PE | Completion of Phase | 2024-11-14 |
CON | Let | 2026-08-13 |
CON | Award Contract | 2026-09-12 |
CON | Notice to Proceed | 2026-10-12 |
ROW | Completion of Phase | 2026-10-15 |
UTL | Completion of Phase | 2026-10-15 |
CON | Start of Phase | 2026-11-15 |
CON | Physical Work Complete | 2028-11-30 |
CON | Completion of Phase | 2028-11-30 |
CON | Project Agreement End Date | 2030-05-31 |