This project includes improvements that will help reduce congestion and increase safety at the intersection of US 202 and SR 926 through lane reconfigurations, striping, upgrades to the traffic signal, signal timing, and bicycle and pedestrian improvements. The roadway improvements for this intersection include installation of a southbound right-turn deceleration lane on US 202 and an additional eastbound left-turn lane on SR 926, creating a double left-turn configuration along the eastbound approach onto Route 202 NB. Pedestrian and bicycle intersection improvements include physical upgrades such as crosswalks, ADA ramps, pedestrian landings, as well signal equipment upgrades for pedestrian push buttons, countdown signal heads, and lighting.

Air Quality Code: R1

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
ROWSTP$99$0$0$0$0
ROW581$24$0$0$0$0
UTL581$31$0$0$0$0
UTLSTP$121$0$0$0$0
CONSTP$3040$0$0$0$0
CON581$760$0$0$0$0
Program Year Totals:$4,075$0$0$0 
Total FY23-FY26 Cost:$4,075Total FY23-FY34 Cost:$4,075 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
ROWPhase Approved by PMC
UTLPhase Approved by PMC
UTLStart of Phase2014-03-28
ROWStart of Phase2014-03-28
UTLCompletion of Phase2016-05-16
ROWCompletion of Phase2016-06-30
ROWPlan to ROW Unit2022-04-01
UTLPlan to Utility Unit2022-04-01
ROW4232 Approved by FHWA
UTLPhase on Approved STIP
ROWPhase on Approved STIP
CONPhase on Approved STIP
CONLet2023-07-13
CONAward Contract2023-08-12
CONStart of Phase2023-09-11
CONNotice to Proceed2023-09-11
CONPhysical Work Complete2025-04-14
CONCompletion of Phase2025-06-13