95429 | US 202 and US 1 Intersection Area Improvements (Chadds Ford Township, Delaware County)

This project is in Concord and Chadds Ford Townships and involves intersection improvements to ease congestion. Improvements include pavement widening, pavement reconstruction and signal upgrades to accommodate an additional northbound US 1 travel lane through the intersection and a double left turn lane for northbound US 202. Other roadway improvements will include landscaped medians throughout the project area; eastbound and westbound left turn lanes and a signalized US 202 pedestrian crossing at the US 202/State Farm Drive/Brandywine Drive intersections; signalized pedestrian crossings at the US 1/Applied Bank Boulevard/State Farm Drive intersection; and elimination of the southbound Route 1 left turn lane at Dickinson Drive. Project CMP commitments include sidewalks, crosswalks, and enhanced bus stop areas in consultation with SEPTA. See DVRPC’s 2013-2014 memorandum on supplemental strategies for details related to this project.

Limits: 202/1 Intersection and Looproad
Air Quality Code: 2030M

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FD581$80$0$0$0$0
FDSTU$320$0$0$0$0
ROW581$38$0$0$0$0
ROWSTP$152$0$0$0$0
UTL581$0$0$0$0$73
UTLSTP$0$0$0$0$294
CONSTP$0$0$0$0$2795
CON581$0$0$0$0$699
Program Year Totals:$590$0$0$0 
Total FY23-FY26 Cost:$590Total FY23-FY34 Cost:$4,451 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
CONPhase Approved by PMC
UTLPhase Approved by PMC
UTLStart of Phase2014-03-28
ROWStart of Phase2014-03-28
UTLCompletion of Phase2016-03-30
ROWCompletion of Phase2016-03-30
ROWPhase Approved by PMC
FD4232 Approved by FHWA
ROW4232 Approved by FHWA
UTL4232 Approved by FHWA
FDStart of Phase2022-09-02
FDPhase on Approved STIP
ROWPhase on Approved STIP
UTLPlan to Utility Unit2023-05-01
ROWPlan to ROW Unit2023-05-01
FDPS+E to District Contract Management2024-04-15
CONLet2024-08-22
CONAward Contract2024-09-21
FDCompletion of Phase2024-10-21
CONStart of Phase2024-10-21
CONNotice to Proceed2024-10-21
CONCompletion of Phase2026-04-24
CONPhysical Work Complete2026-10-23
CONProject Agreement End Date2028-04-22