92807 | PA 73 - Skippack Pike Bridge Replacement (Skippack Township, Montgomery County)
This project involves rehabilitating or replacing the Bridge with minimal roadway improvements at Skippack Pike over Skippack Creek. The improvement is a breakout of MPMS# 88706 for Bridge Rehabilitation. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: over the Skippack Creek
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | NHPP | $300 | $0 | $0 | $0 | $0 |
FD | 185 | $75 | $0 | $0 | $0 | $0 |
ROW | NHPP | $120 | $0 | $0 | $0 | $0 |
ROW | 185 | $30 | $0 | $0 | $0 | $0 |
UTL | 185 | $352 | $0 | $0 | $0 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | BRIP | $5216 | $0 | $0 | $0 | $0 |
Program Year Totals: | $6,093 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $6,093 | Total FY23-FY34 Cost: | $6,093 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Start of Phase | 2013-04-01 |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Completion of Phase | 2016-04-01 |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Let | 2023-08-24 |
CON | Award Contract | 2023-09-23 |
CON | Start of Phase | 2023-10-23 |
CON | Notice to Proceed | 2023-10-23 |
CON | Physical Work Complete | 2025-04-06 |
CON | Completion of Phase | 2025-07-06 |
CON | Project Agreement End Date | 2026-10-05 |