92641 | Dublin Pk o/Morgan Creek (Richland Township, Bucks County)

This project involves rehabilitating or replacing the Bridge at Dublin Pike over Morgan Creek. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.

Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FD185$0$50$50$415$0
ROWBRIP$0$0$0$0$100
UTLBRIP$0$0$0$0$100
CONBRIP$0$0$0$0$4125
Program Year Totals:$0$50$50$415 
Total FY23-FY26 Cost:$515Total FY23-FY34 Cost:$4,840 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDCompletion of Phase2017-03-31
FDPhase Approved by PMC
ROWPhase Approved by PMC
CONPhase Approved by PMC
UTLPhase Approved by PMC
FDPhase on Approved STIP
FDStart of Phase2024-08-30
ROWPlan to ROW Unit2024-11-15
UTLPlan to Utility Unit2024-11-15
FDPS+E to District Contract Management2025-11-13
CONLet2026-02-12
CONAward Contract2026-03-14
CONNotice to Proceed2026-04-13
CONStart of Phase2026-04-13
CONCompletion of Phase2026-10-15
CONPhysical Work Complete2027-10-30
UTLStart of Phase2028-09-30
ROWStart of Phase2028-09-30
CONProject Agreement End Date2029-04-29
ROWCompletion of Phase2031-10-01
UTLCompletion of Phase2031-10-01