92554 | Ridge Ave Over Amtrak (Bridge)
This project invoves rehabiltating or replacing Ridge Avenue (.1 mile SE 29th Street; ) over AMTRAK in Philadelphia. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: 0.1 mile SE 29th Street, Philadelphia
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 185 | $1623 | $0 | $0 | $0 | $0 |
ROW | 185 | $0 | $842 | $0 | $0 | $0 |
UTL | TOLL | $0 | $0 | $0 | $0 | $0 |
UTL | BRIP | $0 | $0 | $0 | $0 | $1434 |
CON | BRIP | $0 | $0 | $0 | $0 | $10150 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $1,623 | $842 | $0 | $0 | ||
Total FY23-FY26 Cost: | $2,465 | Total FY23-FY34 Cost: | $14,049 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Start of Phase | 2022-02-15 |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2024-04-15 |
ROW | Plan to ROW Unit | 2024-05-15 |
FD | PS+E to District Contract Management | 2026-02-12 |
CON | Let | 2026-06-18 |
CON | Award Contract | 2026-07-18 |
FD | Completion of Phase | 2026-08-17 |
CON | Start of Phase | 2026-08-17 |
CON | Notice to Proceed | 2026-08-17 |
CON | Physical Work Complete | 2026-08-23 |
CON | Completion of Phase | 2027-02-28 |
CON | Project Agreement End Date | 2028-02-21 |