92147 | Broad St over Loading Dock (Bridge)
SD bridge breakout project from MPMS #88706.
Broad Street o/ Reading RR
Bridge Replacement
City of Philadelphia
Limits: North of Callohill Road to Noble Street on Broad Street
Philadelphia
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
UTL | STU* | $350 | $0 | $0 | $0 | $0 |
CON | BRIP | $202 | $0 | $0 | $0 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | STU | $723 | $625 | $0 | $0 | $0 |
Program Year Totals: | $1,275 | $625 | $0 | $0 | ||
Total FY23-FY26 Cost: | $1,900 | Total FY23-FY34 Cost: | $1,900 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Start of Phase | 2018-01-15 |
UTL | Plan to Utility Unit | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | 4232 Approved by FHWA | |
UTL | Completion of Phase | 2020-02-24 |
CON | Final Utility Clearance | |
CON | 4232 Approved by FHWA | |
CON | Let | 2020-05-21 |
CON | Award Contract | 2020-06-06 |
CON | Notice to Proceed | 2020-06-22 |
CON | Start of Phase | 2020-06-22 |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Physical Work Complete | 2022-11-28 |
CON | Completion of Phase | 2024-03-29 |
CON | Project Agreement End Date | 2024-04-13 |