90550 | Creamery Rd & Tohickon Cr (Bridge) (Bedminster Township, Bucks County)
This project involves rehabilitating or replacing the Creamery Road and Tohickon Creek. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization. Improvements also include associated roadway approach reconstruction, guiderail and drainage improvements.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: North of Sweetbriar Rd over Tokickon Creek on Creamery Road.
Bedminster Township, Bucks County
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | STU | $0 | $0 | $950 | $0 | $0 |
ROW | 185 | $0 | $0 | $0 | $0 | $250 |
UTL | 185 | $0 | $0 | $0 | $0 | $50 |
CON | 185 | $0 | $0 | $0 | $0 | $5000 |
Program Year Totals: | $0 | $0 | $950 | $0 | ||
Total FY23-FY26 Cost: | $950 | Total FY23-FY34 Cost: | $6,250 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
FD | Phase Approved by PMC | |
UTL | Completion of Phase | 2022-12-30 |
UTL | Start of Phase | 2023-06-01 |
FD | Start of Phase | 2023-10-11 |
ROW | Plan to ROW Unit | 2023-12-18 |
UTL | Plan to Utility Unit | 2023-12-18 |
FD | PS+E to District Contract Management | 2024-10-01 |
CON | Let | 2025-01-09 |
CON | Award Contract | 2025-02-08 |
CON | Notice to Proceed | 2025-03-10 |
CON | Start of Phase | 2025-03-10 |
FD | Completion of Phase | 2025-03-10 |
CON | Physical Work Complete | 2026-03-10 |
CON | Project Agreement End Date | 2027-09-08 |
CON | Completion of Phase | 2027-09-10 |
ROW | Start of Phase | 2030-09-30 |
ROW | Completion of Phase | 2033-10-01 |