88085 | Byberry Road Bridge Replacement
This project involves rehabilitating or replacing the Bridge at Byberry Road over CSX Rail Line. The improvement is a breakout of MPMS# 88706 for Bridge Rehabilitation. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Byberry Road over CSX Rail Line
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
ROW | STU* | $87 | $0 | $0 | $0 | $0 |
UTL | STU* | $699 | $0 | $0 | $0 | $0 |
CON | BRIP | $7053 | $1610 | $1483 | $2766 | $500 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $7,839 | $1,610 | $1,483 | $2,766 | ||
Total FY23-FY26 Cost: | $13,698 | Total FY23-FY34 Cost: | $14,198 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | 4232 Approved by FHWA | |
ROW | 4232 Approved by FHWA | |
UTL | Plan to Utility Unit | 2018-09-15 |
ROW | Plan to ROW Unit | 2019-02-07 |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Award Contract | 2023-08-28 |
CON | Start of Phase | 2023-09-27 |
CON | Notice to Proceed | 2023-09-27 |
CON | Let | 2023-11-02 |
CON | Physical Work Complete | 2025-08-02 |
CON | Completion of Phase | 2026-04-16 |
CON | Project Agreement End Date | 2027-01-31 |