87107 | School District of Philadelphia Improvement (SRTSF) - Round 1 (Philadelphia City)
This project will improve walking routes in the 37 District K-8 schools to increase safety for students who walk or bike to school. The sidewalks on the streets bordering the targeted schools are in varying states of disrepair, presenting a danger to students walking or riding their bicycles to school. This project will repair the sidewalks by removing cracked, raised, and broken concrete blocksthat make the sidewalks uneven and filling the spaces with new concrete in order to create a smooth, even, hard surface safe for walking and bike riding. Bike racks will also be installed in convenient locations within school boundaries.
This project was awarded $1,000,439 in federal Safe Routes to School (SRTSF) funding in May of 2009.
Limits: Vicinity of Philadelphia District Schools
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | SRTSF | $0 | $0 | $0 | $0 | $1000 |
CON | TAP | $754 | $0 | $0 | $0 | $0 |
Program Year Totals: | $754 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $754 | Total FY23-FY34 Cost: | $1,754 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Final Utility Clearance | |
CON | 4232 Approved by FHWA | |
CON | Start of Phase | 2023-04-24 |
CON | Let | 2023-05-25 |
CON | Award Contract | 2023-06-24 |
CON | Notice to Proceed | 2023-08-21 |
CON | Physical Work Complete | 2024-11-29 |
CON | Completion of Phase | 2025-01-28 |
CON | Project Agreement End Date | 2026-05-30 |