85949 | SR 896 Safety Improvement (London Britain Township & New London Township, Chester County)

The scope of work for this project was developed from the Road Safety Audit which was conducted in November 2006 and undertaken by DVRPC in conjunction with the Pennsylvania Department of Transportation. The purpose of this project is to reduce the number of crashes and related injuries and severity of the crashes which occur along the approximate five mile section of PA Route 896, between Elbow Lane in London Britain Township and Shepherd Lane in New London Township. This project will include: Increasing the lane width and shoulder width along PA Route 896; removing severe vertical crests at select locations; installing left turn lanes at select intersections; constructing a roundabout at the PA Route 896/PA Route 841 intersection; modifying the geometry at select intersections; improving drainage along PA Route 896; repaving PA Route 896 with pavement reconstruction at selection locations; relocating select utility poles; installing appropriate signage along PA Route 896; installing raised pavement markers (RPM), delineators, and rumble strips along PA Route 896. Estimated total project cost is $13,800,000. PE ($2,500,000 estimate), FD ($2,800,000 estimate), ROW ($1,500,000 estimate), UTL ($500,000 estimate), and CON ($6,500,000 estimate).

Limits: PA 896, Elbow Lane to Shepherd Lane
Air Quality Code: 2035M

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
ROWTOLL$0$0$0$0$0
ROWHSIP*$900$0$0$0$0
UTLTOLL$0$0$0$0$0
UTLHSIP*$100$0$0$0$0
CONHSIP$1809$7961$0$0$0
CONSTU$0$3100$0$0$0
CONTOLL$0$0$0$0$0
Program Year Totals:$2,809$11,061$0$0 
Total FY23-FY26 Cost:$13,870Total FY23-FY34 Cost:$13,870 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
UTLPhase Approved by PMC
ROWStart of Phase2009-01-29
UTLStart of Phase2009-01-29
UTLCompletion of Phase2016-05-30
ROWCompletion of Phase2016-12-23
ROWPhase Approved by PMC
ROWPlan to ROW Unit2020-07-15
UTL4232 Approved by FHWA
ROW4232 Approved by FHWA
UTLPhase on Approved STIP
CONPhase on Approved STIP
ROWPhase on Approved STIP
UTLPlan to Utility Unit2020-06-15
CONLet2023-09-15
CONAward Contract2023-10-20
CONNotice to Proceed2023-11-19
CONStart of Phase2023-11-19
CONPhysical Work Complete2025-03-07
CONProject Agreement End Date2026-09-05
CONCompletion of Phase2026-09-11