84284 | Doe Run Rd/Buck Run (Bridge) (West Marlborough Township, Chester County)
This project involves rehabilitating or replacing the Bridge at Doe Run Road over Black Run. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Chester County
West Marlborough Township
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | STU | $0 | $0 | $450 | $0 | $0 |
ROW | 185 | $0 | $0 | $0 | $0 | $100 |
UTL | 185 | $0 | $0 | $0 | $0 | $50 |
CON | 185 | $0 | $0 | $0 | $0 | $2000 |
Program Year Totals: | $0 | $0 | $450 | $0 | ||
Total FY23-FY26 Cost: | $450 | Total FY23-FY34 Cost: | $2,600 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Start of Phase | 2023-10-01 |
ROW | Start of Phase | 2024-03-18 |
UTL | Start of Phase | 2024-03-18 |
UTL | Plan to Utility Unit | 2024-05-01 |
ROW | Plan to ROW Unit | 2024-06-01 |
UTL | Completion of Phase | 2025-03-31 |
FD | PS+E to District Contract Management | 2025-12-01 |
CON | Let | 2026-03-26 |
ROW | Completion of Phase | 2026-03-31 |
FD | Completion of Phase | 2026-03-31 |
CON | Award Contract | 2026-04-25 |
CON | Notice to Proceed | 2026-05-25 |
CON | Start of Phase | 2026-05-25 |
CON | Physical Work Complete | 2027-07-30 |
CON | Completion of Phase | 2027-09-28 |
CON | Project Agreement End Date | 2029-01-27 |