84256 | Old Street Rd/SEPTA (Bensalem Township & Lower Southampton Township, Bucks County)

Old Street Road over SEPTA West Trenton Bridge
Bensalem and Lower Southampton Townships
Structure may be rehabilitated or replaced.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.

Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PE185$0$95$0$0$0
PESTU$0$380$0$0$0
FDSTU$0$536$0$0$0
FDSTP$509$0$0$0$0
FD185$127$134$0$0$0
ROWSTP$0$44$0$0$0
ROW185$0$11$0$0$0
UTLTOLL$0$0$0$0$0
UTLBRIP$0$0$0$464$0
CONTOLL$0$0$0$0$0
CONBRIP$0$0$0$3710$0
Program Year Totals:$636$1,200$0$4,174 
Total FY23-FY26 Cost:$6,010Total FY23-FY34 Cost:$6,010 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
UTLStart of Phase2016-06-15
UTLPhase Approved by PMC
CONPhase Approved by PMC
CONPhase on Approved STIP
ROWPhase on Approved STIP
ROWPhase Approved by PMC
UTLPhase on Approved STIP
FDPhase on Approved STIP
FDPhase Approved by PMC
FDStart of Phase2023-06-14
UTLCompletion of Phase2023-06-15
ROWPlan to ROW Unit2023-09-15
UTLPlan to Utility Unit2024-03-15
FDPS+E to District Contract Management2024-06-15
CONLet2024-09-26
CONAward Contract2024-10-26
CONNotice to Proceed2024-11-25
FDCompletion of Phase2024-11-25
CONStart of Phase2024-11-25
CONPhysical Work Complete2025-11-29
CONCompletion of Phase2026-01-28
CONProject Agreement End Date2027-05-30