83742 | Keim Street Bridge Over Schuylkill River (Pottstown Borough & North Coventry Township, Montgomery County)

This project is the replacement of the existing bridge carrying South Keim Street over the Schuylkill River with minor approach roadway work. Additionally, there will be widening of Industrial Highway, to accommodate a right lane along the eastbound side and a left turn lane along the westbound side. The project is located in the Borough of Pottstown in Montgomery County and North Coventry Township in Chester County. The bridge is currently closed to traffic. A programmatic agreement has been signed by all parties for the replacement of this structure.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.

Limits: Over Schuylkill River
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FDSTU$120$0$0$0$0
FDLOC$8$0$0$0$0
FD183$22$0$0$0$0
ROW183$37$3$0$0$0
ROWSTU$200$16$0$0$0
ROWLOC$13$1$0$0$0
UTLSTP$54$0$0$0$0
UTL183$10$0$0$0$0
UTLLOC$4$0$0$0$0
CONLOC$0$62$309$556$0
CONSTP$0$0$4946$8892$0
CONSTU$0$1000$0$0$0
CON183$0$187$927$1667$0
Program Year Totals:$468$1,269$6,182$11,115 
Total FY23-FY26 Cost:$19,034Total FY23-FY34 Cost:$19,034 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
UTLPhase Approved by PMC
CONPhase Approved by PMC
UTLStart of Phase2015-04-15
ROWStart of Phase2015-04-15
UTLCompletion of Phase2016-04-15
FDCompletion of Phase2016-05-16
ROWPhase Approved by PMC
FD4232 Approved by FHWA
ROW4232 Approved by FHWA
FDStart of Phase2020-09-15
UTLPlan to Utility Unit2020-11-15
ROWPlan to ROW Unit2021-06-20
UTL4232 Approved by FHWA
ROWCompletion of Phase
ROWPhase on Approved STIP
UTLPhase on Approved STIP
FDPhase on Approved STIP
CONPhase on Approved STIP
FDPS+E to District Contract Management2023-06-14
CONLet2023-09-14
CONStart of Phase2023-09-25
CONNotice to Proceed2023-09-25
CONAward Contract2023-10-14
CONCompletion of Phase2024-02-14
CONPhysical Work Complete2025-08-30
CONProject Agreement End Date2027-02-28