83736 | Roosevelt Blvd over Wayne Junction (WAV) (Bridge) (Philadelphia City)
This project involves rehabilitating or replacing the bridge carrying Roosevelt Boulevard US 1 over Roberts Road, Wayne Avenue Station, Clarissa Street, Germantown Avenue, and N. Gratz Street. The existing bridge is 2,589 feet in length and carries two 12-foot northbound lanes, three 12-foot southbound lanes, shoulders, and a center median barrier. The rehabilitation will include deck replacement, superstructure and substructure repairs, bridge painting, bearing maintenance, evaluation of pin & hangers, fatigue analysis, and seismic analysis. The project will be constructed under traffic. This project will also include the rehabilitation of the Fox Street Bridge over US 1.
Limits: Over Wayne Junction
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
UTL | NHPP* | $690 | $0 | $0 | $0 | $0 |
CON | NHPP* | $2500 | $0 | $0 | $0 | $0 |
CON | NHPP | $0 | $10000 | $5955 | $0 | $0 |
CON | 581 | $0 | $3125 | $1489 | $0 | $0 |
Program Year Totals: | $3,190 | $13,125 | $7,444 | $0 | ||
Total FY23-FY26 Cost: | $23,759 | Total FY23-FY34 Cost: | $23,759 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
UTL | Start of Phase | 2009-10-15 |
UTL | Phase Approved by PMC | |
UTL | 4232 Approved by FHWA | |
UTL | Plan to Utility Unit | |
CON | Final Utility Clearance | |
UTL | Completion of Phase | 2018-08-15 |
CON | 4232 Approved by FHWA | |
CON | Final ROW Clearance | |
CON | Let | 2018-10-18 |
CON | Award Contract | 2018-11-05 |
CON | Start of Phase | 2018-12-26 |
CON | Notice to Proceed | 2018-12-03 |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Completion of Phase | 2022-11-10 |
CON | Physical Work Complete | 2023-09-06 |
CON | Project Agreement End Date | 2024-06-02 |