This project involves rehabilitating or replacing the bridge carrying Roosevelt Boulevard US 1 over Roberts Road, Wayne Avenue Station, Clarissa Street, Germantown Avenue, and N. Gratz Street. The existing bridge is 2,589 feet in length and carries two 12-foot northbound lanes, three 12-foot southbound lanes, shoulders, and a center median barrier. The rehabilitation will include deck replacement, superstructure and substructure repairs, bridge painting, bearing maintenance, evaluation of pin & hangers, fatigue analysis, and seismic analysis. The project will be constructed under traffic. This project will also include the rehabilitation of the Fox Street Bridge over US 1.

Limits: Over Wayne Junction
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
UTLNHPP*$690$0$0$0$0
CONNHPP*$2500$0$0$0$0
CONNHPP$0$10000$5955$0$0
CON581$0$3125$1489$0$0
Program Year Totals:$3,190$13,125$7,444$0 
Total FY23-FY26 Cost:$23,759Total FY23-FY34 Cost:$23,759 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
UTLStart of Phase2009-10-15
UTLPhase Approved by PMC
UTL4232 Approved by FHWA
UTLPlan to Utility Unit
CONFinal Utility Clearance
UTLCompletion of Phase2018-08-15
CON4232 Approved by FHWA
CONFinal ROW Clearance
CONLet2018-10-18
CONAward Contract2018-11-05
CONStart of Phase2018-12-26
CONNotice to Proceed2018-12-03
UTLPhase on Approved STIP
CONPhase on Approved STIP
CONCompletion of Phase2022-11-10
CONPhysical Work Complete2023-09-06
CONProject Agreement End Date2024-06-02