79830 | North Delaware Riverfront Greenway Project, Sec 1 (TAP) (Philadelphia City)
The project is a 12' wide multi-use trail extending the completed K&T Trail Phase 1 (MPMS 61712) at Magee Avenue and continuing along the Delaware River to the Tacony Boat Launch at Princeton Avenue.
In the fall of 2015, PennDOT held a competitive round for statewide TAP funding. This project was one of 13 projects across the DVRPC region that was awarded funding in January 2017 through the statewide TAP program (MPMS #60560), receiving $1,000,000 out of the $9.4 million awarded to the region.
PA ID: PA242, PA251, PA262, PA615.
Limits: City of Philadelphia
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAP | $500 | $500 | $0 | $0 | $0 |
Program Year Totals: | $500 | $500 | $0 | $0 | ||
Total FY23-FY26 Cost: | $1,000 | Total FY23-FY34 Cost: | $1,000 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final Utility Clearance | |
CON | Final ROW Clearance | |
CON | 4232 Approved by FHWA | |
CON | Let | 2022-05-12 |
CON | Award Contract | 2022-06-12 |
CON | Phase on Approved STIP | |
CON | Start of Phase | 2022-10-31 |
CON | Notice to Proceed | 2022-08-08 |
CON | Completion of Phase | 2024-02-12 |
CON | Physical Work Complete | 2024-08-06 |
CON | Project Agreement End Date | 2026-02-04 |