77211 | PA 309 Connector: Allentown Road to Souderton Pike (HT2) (Franconia Township, Hatfield Township & Hilltown Township, Montgomery County)
The PA 309 Connector Project is intended to create an improved connection between PA 63 (near the Lansdale Interchange of I-476) and PA 309 (near the southern terminus of the Sellersville Bypass) in Bucks County. Phase 1, which created a bypass around Mainland village in Montgomery County and reconstructed and widened Wambold Road from PA 63 (Sumneytown Pike to Allentown Road, was carried under MPMS #16438.
Phase 2 will include the following improvements:
- Extend Wambold Road past its current end at Allentown Road up to the intersection of Cowpath Road and Township Line Road;
- Reconstruct and widen Township Line Road from Cowpath Road to Souderton Pike;
- Realign and signalize the intersection of Penn Street and Township Line Road;
- Signalize the intersection of Township Line Road and Souderton Pike.
Phase 3 will reconstruct and widen Township Line Road between Souderton Pike and the Sellersville Bypass, make a physical connection to PA 309, and is listed under MPMS #105803.
Project CMP (Congestion Management Process) commitments include signal and intersection improvements, turning movement enhancements, accommodations for pedestrians and bicyclists, coordination with SEPTA, and outreach to employers to promote transportation demand management strategies. See DVRPC’s 2016-2017 memorandum on supplemental strategies for details related to this project.
Limits: Allentown Road to Souderton Pike
Air Quality Code: 2035M
FY2023 TIP for PA Program Years (in Thousands)
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|
CON | STU* | $5102 | $1037 | $0 | $0 | $0 |
CON | STP* | $7363 | $0 | $0 | $0 | $0 |
Program Year Totals: | $12,465 | $1,037 | $0 | $0 | |
Total FY23-FY26 Cost: | $13,502 | Total FY23-FY34 Cost: | $13,502 | |
All costs in thousands. |
Milestones
Phase | Milestone | Estimated Date |
---|
CON | Phase Approved by PMC | |
CON | Final Utility Clearance | |
CON | Final ROW Clearance | |
CON | 4232 Approved by FHWA | |
CON | Start of Phase | 2021-10-13 |
CON | Let | 2021-10-21 |
CON | Award Contract | 2021-09-13 |
CON | Notice to Proceed | 2021-12-06 |
CON | Phase on Approved STIP | |
CON | Completion of Phase | 2024-11-30 |
CON | Project Agreement End Date | 2026-04-01 |
CON | Physical Work Complete | 2027-10-22 |