74827 | Delaware Canal Enhancement (Bristol Borough & Yardley Borough, Bucks County)

The proposed structure will be a single span pre-stressed concrete adjacent box beam bridge for the Aqueduct and a pre-stressed concrete adjacent box beam bridge for the Tow Path.
The existing Delaware Canal Aqueduct and Tow Path Bridge are located over Brock Creek in Delaware Canal State Park, Yardley Borough. The Delaware Canal runs in a northwest to southwest direction through Yardley, almost parallel to Main Street. The Aqueduct is just northwest of the crossing of S.R. 332/Afton Avenue and carries the Delaware Canal over Brock Creek. At the project location, the Delaware River flows parallel to the Delaware Canal approximately 1000 feet northeast of the site.
The existing Aqueduct is a single span reinforced concrete u-slab, having a 24-inch depth, with reinforced concrete abutments and wingwalls. The existing tow path bridge is a single span reinforced concrete arch located on the same substructure as the aqueduct, although it appears to have been constructed at different times. Both of the structures have a clear span of 27.3' and are located on a skew of approximately 61° to Brock Creek. The structures of interest are located in a very flood prone location. It is believed that the low under clearance and short span of the existing aqueduct coupled with debris further reducing the hydraulic opening is the primary reason for flooding.

Limits: Over Brock Creek, Yardley to Bristol Boroughs
Air Quality Code: X12

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
CONSTU$0$0$464$564$0
CONTOLL$0$0$0$0$0
CONSTP$0$0$0$0$665
Program Year Totals:$0$0$464$564 
Total FY23-FY26 Cost:$1,028Total FY23-FY34 Cost:$1,693 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONFinal Utility Clearance2010-12-30
CONPhase Approved by PMC
CONPhase on Approved STIP
CONLet2025-09-11
CONAward Contract2025-10-11
CONStart of Phase2025-11-10
CONNotice to Proceed2025-11-10
CONCompletion of Phase2025-11-16
CONPhysical Work Complete2026-10-03
CONProject Agreement End Date2028-04-02