74813 | Ambler Pedestrian Sidewalk Improvements (Ambler Borough, Montgomery County)
Ambler streetscape improvement including curb and sidewalk reconstruction along Orange, Highland, Southern, Park, and Spring Avenues.
Any additional funds required to complete the project will be provided locally.
SAFETEA DEMO #2058 - $520,000. PA ID #425. $354,000 DEMO applied to this project. Also see MPMS #48173.
Limits: Orange Avenue/Highland Avenue/Southern Park Avenue
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | STP | $0 | $365 | $0 | $0 | $0 |
Program Year Totals: | $0 | $365 | $0 | $0 | ||
Total FY23-FY26 Cost: | $365 | Total FY23-FY34 Cost: | $365 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final Utility Clearance | |
CON | Cash Flow Start | 2016-10-14 |
CON | Cash Flow End | 2017-03-14 |
CON | Phase on Approved STIP | |
CON | Notice to Proceed | 2022-12-29 |
CON | Start of Phase | 2023-03-29 |
CON | Let | 2023-06-01 |
CON | Award Contract | 2023-07-01 |
CON | Completion of Phase | 2024-07-22 |
CON | Physical Work Complete | 2025-01-20 |
CON | Project Agreement End Date | 2026-07-21 |