70245 | Chester City Access Improvements II (Chester City, Delaware County)
This project entails the improvement of the Chestnut Street and Morton Avenue corridor which provides mobility between I-95 and PA 291 in the City of Chester. Specifically, work includes the widening of Chestnut Street from I-95 to 10th Street without adding additional travel lanes, and the reconfiguration of the intersections at 12th /Chestnut St., Chestnut St./10th St./ Morton Ave. (SR 0013), and Morton/Potter/5th/6th. Also includes drainage improvements, signalization and signing improvements along the corridor; vertical clearance improvements at the Amtrak overpass; and minor rehabilitation and painting of the I-95 overpass and maintenance of traffic during construction. This project was broken out from MPMS # 57780/TIP #7915.
This road segment is included in the Delaware County Bicycle Plan. SEPTA's Route 113 bus uses Morton Avenue.
A final alternative for bridge rehabilitation or replacement is determined upon National Environmental Policy Act (NEPA) clearance.
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 581 | $41 | $0 | $0 | $0 | $0 |
FD | STU | $165 | $0 | $0 | $0 | $0 |
Program Year Totals: | $206 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $206 | Total FY23-FY34 Cost: | $206 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
FD | 4232 Approved by FHWA | |
FD | Cash Flow Start | 2012-05-04 |
FD | Start of Phase | 2012-02-16 |
FD | PS+E to District Contract Management | 2016-01-11 |
FD | Cash Flow End | 2016-05-11 |
FD | Completion of Phase | 2016-07-25 |
FD | Phase on Approved STIP |