70231 | Swanson Street Reconstruction (Philadelphia City)

Reconstruction of the existing roadway to provide a new roadway surface, including footway, medians and curbs, new drainage and stormwater improvements (including GSI where appropriate), street lighting, pavement markings, landscaping and a new signal at the Snyder Avenue intersection.

Limits: Delaware Avenue to Oregon Avenue
Air Quality Code: S10

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FDSTP$1613$0$0$0$0
FDLOC$403$0$0$0$0
ROWSTU*$7046$0$0$0$0
CONSTP$0$0$0$0$1872
CONLOC$0$0$979$1066$1670
CONSTU$0$0$3918$4264$4807
Program Year Totals:$9,062$0$4,897$5,330 
Total FY23-FY26 Cost:$19,289Total FY23-FY34 Cost:$27,638 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
FDCompletion of Phase2011-07-15
ROWPhase Approved by PMC
FDPhase Approved by PMC
ROWStart of Phase2021-04-01
ROW4232 Approved by FHWA
FD4232 Approved by FHWA
FDStart of Phase2021-02-06
CONPhase on Approved STIP
ROWPhase on Approved STIP
FDPhase on Approved STIP
ROWCompletion of Phase2022-04-01
ROWPlan to ROW Unit2025-08-15
FDPS+E to District Contract Management2025-10-15
CONLet2026-01-15
CONAward Contract2026-02-16
CONNotice to Proceed2026-03-19
CONStart of Phase2026-03-19
CONPhysical Work Complete2028-01-15
CONProject Agreement End Date2029-07-15
CONCompletion of Phase2031-05-02