64798 | North Narberth Avenue Bridge Over Amtrak/SEPTA (CB) (Narberth Borough, Montgomery County)
This project involves rehabilitating or replacing a borough owned, through girder type bridge. The bridge currently has one sidewalk. This project is subject to standard PENNDOT design procedures as defined in the Bicycle/Pedestrian Facilities checklist. The bicycle and pedestrian checklists will be incorporated into the project. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Over Amtrak/SEPTA Paoli
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | 183 | $0 | $0 | $0 | $0 | $159 |
CON | 581 | $0 | $16 | $298 | $1 | $321 |
CON | LOC | $0 | $6 | $99 | $1 | $160 |
CON | BOF | $0 | $88 | $1590 | $2 | $2559 |
Program Year Totals: | $0 | $110 | $1,987 | $4 | ||
Total FY23-FY26 Cost: | $2,101 | Total FY23-FY34 Cost: | $5,300 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final ROW Clearance | |
CON | Phase on Approved STIP | |
CON | Let | 2024-01-11 |
CON | Award Contract | 2024-02-12 |
CON | Start of Phase | 2024-03-12 |
CON | Notice to Proceed | 2024-03-12 |
CON | Completion of Phase | 2024-05-16 |
CON | Physical Work Complete | 2025-06-30 |
CON | Project Agreement End Date | 2026-12-29 |