64791 | Kedron Avenue @ Franklin (Ridley Township, Delaware County)
Existing signalization and geometry is outdated. Substandard signal head configuration and size create a safety hazard. Roadway geometry is not adequate for proper turn movements, especially for buses. Traffic movement is impacted by inability of buses to negotiate turns. Intersection is heavily used by both SEPTA Route 107 and school buses. Proposed solution would be modernization of signals and improving the turn radius at the northeast and southeast corners of the intersection. Pedestrian Hand/Man signals with countdown indicators will be provided at each crossing. Project would alleviate safety problems and enhance turning movements. Design and ROW are being advanced by the township.
This road segment is included in the Delaware County Bicycle Plan.
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | LOC | $159 | $0 | $0 | $0 | $0 |
CON | CAQ | $483 | $50 | $0 | $0 | $0 |
Program Year Totals: | $642 | $50 | $0 | $0 | ||
Total FY23-FY26 Cost: | $692 | Total FY23-FY34 Cost: | $692 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
FD | Completion of Phase | 2016-08-15 |
CON | Phase Approved by PMC | |
CON | Completion of Phase | 2021-01-29 |
FD | Start of Phase | 2022-06-19 |
CON | Final Utility Clearance | |
FD | PS+E to District Contract Management | 2022-06-01 |
CON | 4232 Approved by FHWA | |
CON | Let | 2022-08-25 |
CON | Award Contract | 2022-09-24 |
CON | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Notice to Proceed | 2022-10-11 |
CON | Start of Phase | 2022-10-24 |
CON | Physical Work Complete | 2024-03-07 |
CON | Project Agreement End Date | 2025-09-05 |