64791 | Kedron Avenue @ Franklin (Ridley Township, Delaware County)

Existing signalization and geometry is outdated. Substandard signal head configuration and size create a safety hazard. Roadway geometry is not adequate for proper turn movements, especially for buses. Traffic movement is impacted by inability of buses to negotiate turns. Intersection is heavily used by both SEPTA Route 107 and school buses. Proposed solution would be modernization of signals and improving the turn radius at the northeast and southeast corners of the intersection. Pedestrian Hand/Man signals with countdown indicators will be provided at each crossing. Project would alleviate safety problems and enhance turning movements. Design and ROW are being advanced by the township.
This road segment is included in the Delaware County Bicycle Plan.

Limits: At Franklin Avenue
Air Quality Code: R1

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FDLOC$159$0$0$0$0
CONCAQ$483$50$0$0$0
Program Year Totals:$642$50$0$0 
Total FY23-FY26 Cost:$692Total FY23-FY34 Cost:$692 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
FDCompletion of Phase2016-08-15
CONPhase Approved by PMC
CONCompletion of Phase2021-01-29
FDStart of Phase2022-06-19
CONFinal Utility Clearance
FDPS+E to District Contract Management2022-06-01
CON4232 Approved by FHWA
CONLet2022-08-25
CONAward Contract2022-09-24
CONPhase on Approved STIP
FDPhase on Approved STIP
CONNotice to Proceed2022-10-11
CONStart of Phase2022-10-24
CONPhysical Work Complete2024-03-07
CONProject Agreement End Date2025-09-05