❮ Back

63486 | US 202, Johnson Highway to Township Line Road (61S) (Whitpain Township, East Norriton Township & Norristown Borough, Montgomery County)

This project provides for the widening of US 202 for approximately 1.8 miles from two lanes to five lanes including a center turn lane in this section of US 202 between Johnson Highway and Township Line Road in Norristown Borough, East Norriton & Whitpain Twps. One bridge and one culvert will be replaced in this portion of Section 600. Traffic signal equipment will be replaced at the intersections with Johnson Highway, Germantown Pike and Township Line Road. Bike lanes adjacent to the outside travel lane will be provided in both the northbound and southbound directions. This section is designed under Section 610. ITS elements are included in this project. MPMS #50364 (US 202 Sec 610) contains the final design funding for this project. See MPMS #'s 63491, 63486, and 63490 for construction sections.
In the DVRPC region, US 202 covers 61 miles, traversing 27 municipalities in Delaware, Chester, Montgomery, and Bucks counties. For planning purposes, US 202 has been divided into seven major sections (100 through 700), and some of those sections have been broken down further to simplify construction management.
Project CMP (Congestion Management Process) commitments include strategies such as improvements for transit users, bicyclists, pedestrians, and drivers on the existing road network (operations). See DVRPC’s 2007 annual memoranda on supplemental strategies for details related to this project.

Limits: Johnson Highway to Township Line Road
Air Quality Code: 2035M

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
CONTOLL$0$0$0$0$0
CONNHPP*$10000$5000$0$0$0
Program Year Totals:$10,000$5,000$0$0 
Total FY23-FY26 Cost:$15,000Total FY23-FY34 Cost:$15,000 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONFinal ROW Clearance
CON4232 Approved by FHWA
CONLet2021-01-14
CONAward Contract2021-02-28
CONNotice to Proceed2021-03-01
CONStart of Phase2021-03-29
CONPhase on Approved STIP
CONCompletion of Phase2029-08-29
CONPhysical Work Complete2029-12-30
CONProject Agreement End Date2031-06-30