60651 | Substations and Power Improvements (Various, SEPTA)

These projects will replace existing equipment with modern indoor switchgear and state-of-the-art industry safety systems, communications and relay protection systems, and will provide additional power and reliability. Work includes replacing transformers, trolley breakers, feeder switches, substation switchgears and protective relaying. Power infrastructure must also be brought to a state of good repair. This includes replacing catenary systems and upgrading 80+ year old Regional Rail infrastructure. Additional power improvements will be undertaken as part of the Infrastructure Safety Renewal Program (ISRP) MPMS #90497.
Currently programmed substation and power projects include:
Multimodal Substation Overhaul Program:
- Supervisory Control and Data Acquisition (SCADA) System and Network Upgrade - $18.50M (FY 2028 – FY 2034)
- Substation Design and Equipment Purchase - $28.23M (Prior Years – FY 2024)
Power Program:
- 30th Street West Catenary Replacement - $77.00M (Prior Years – FY 2027)
Railroad Substation:
- Railroad Substation 18th Street Switching Station - $13M (FY 2023 – FY 2025)
- Railroad Substation Brill - $12.8M (FY 2025 – FY 2028)
- Railroad Substation Chestnut Hill - $22.54M (FY2022 – FY 2026)
- Railroad Substation Cresheim Valley - $25.79M (FY 2022 – FY 2026)
- Railroad Substations Lansdale, Hatboro, & 12th/Portal - $31.54M ( FY 2019 – FY 2022)
- Wayne Junction Static Frequency Converters #1-4 - $85.70 (Design - Prior Years - FY2021) (Construction - FY 2022 – FY 2027)
- Railroad Substation Woodbourne - $23.79M (FY2023 - FY2026)
Transit Substations Program:
- Transit Substation Ellen - $12.68M (FY 2025 – FY 2028)
- Transit Substation Market - $12.50M (FY 2022- FY2024)
- Transit Substations Park, Broad, Louden, Castor - $19.95M (FY2022 - FY2024)
- Transit Substation Ranstead - $12.68M (FY 2027– FY 2029)
Transit Substation Program - $140M (FY 2028 - FY 2034)

Limits: System-wide railroad substations
Air Quality Code: M6

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
ERCLOC$365$165$182$266$942
ERC1514$9580$4946$5466$7976$28245
ERC5337$2063$63979$22594$32966$116746
ERCOTH$15000$5000$14000$0$125120
Program Year Totals:$27,008$74,090$42,242$41,208 
Total FY23-FY26 Cost:$184,548Total FY23-FY34 Cost:$455,601 
All costs in thousands.

No milestones are available for this project.