57865 | Edge Hill Road Reconstruction (Abington Township, Montgomery County)
The purpose of this project is to provide for the safe movement of vehicles and pedestrians on Edge Hill Road and Tyson Avenue between Easton Road and Jenkintown Road. The existing roadway consists of 11’ lanes and intermittent shoulders used for parking. The proposed roadway will consist of 11’ lanes and 2’ minimum shoulders. Parking areas will be provided where feasible. Sidewalk will be constructed where feasible (currently there are no sidewalks). The roadway will be milled and resurfaced where feasible.
Limits: Easton Road to Jenkintown Road
Air Quality Code: S10
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | STU | $373 | $0 | $0 | $0 | $0 |
CON | 581 | $93 | $0 | $0 | $0 | $0 |
Program Year Totals: | $466 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $466 | Total FY23-FY34 Cost: | $466 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final ROW Clearance | |
CON | Final Utility Clearance | |
CON | 4232 Approved by FHWA | |
CON | Let | 2018-09-27 |
CON | Award Contract | 2018-10-27 |
CON | Start of Phase | 2018-09-25 |
CON | Notice to Proceed | 2018-11-13 |
CON | Completion of Phase | 2021-03-11 |
CON | Physical Work Complete | 2022-09-30 |
CON | Phase on Approved STIP | |
CON | Project Agreement End Date | 2024-03-29 |