57619 | Route 313 Corridor Improvements (New Britain Township & Plumstead Township, Bucks County)

This project includes corridor improvements along PA 313 (Swamp Road). Project provides for intersection improvements (left turn lanes) at PA 313 and Ferry Road. A center left turn lane will be provided for the length of the project. Two bridges will be reconstructed.
SAFETEA DEMO #2662, PA ID# 466 - $1.6 MILLION

Limits: Ferry Road to Broad Street
Air Quality Code: R1

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
ROWNHPP$192$0$0$0$0
ROW581$48$0$0$0$0
UTL581$85$0$0$0$0
UTLNHPP$339$0$0$0$0
CONNHPP$0$0$6993$10489$0
Program Year Totals:$664$0$6,993$10,489 
Total FY23-FY26 Cost:$18,146Total FY23-FY34 Cost:$18,146 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
ROWPhase Approved by PMC
ROW4232 Approved by FHWA
ROWStart of Phase2015-05-26
CONPhase Approved by PMC
ROWCash Flow Start2016-01-08
UTLPhase Approved by PMC
UTLStart of Phase2018-06-18
ROWCash Flow End2018-09-24
ROWCompletion of Phase2018-09-24
UTLCompletion of Phase2020-12-30
ROWPlan to ROW Unit
UTLPlan to Utility Unit2021-07-01
CONPhase on Approved STIP
ROWPhase on Approved STIP
UTLPhase on Approved STIP
UTL4232 Approved by FHWA
CONLet2024-01-11
CONAward Contract2024-02-12
CONStart of Phase2024-03-12
CONNotice to Proceed2024-03-12
CONCompletion of Phase2024-11-06
CONPhysical Work Complete2025-12-31
CONProject Agreement End Date2027-07-01