50646 | PA 63 Bridges (3) Over Unami Creek and East Branch of Perkiomen (Marlborough Township & Upper Salford Township, Montgomery County)
This project involves the rehabilitating or replacing three bridges on Route 63 Between PA 113 and PA 29, over the Unami Creek and the East Branch of the Perkiomen Creek.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Over Unami Creek and East Branch of Perkiomen
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | STU | $198 | $0 | $0 | $0 | $0 |
CON | 581 | $49 | $0 | $0 | $0 | $0 |
Program Year Totals: | $247 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $247 | Total FY23-FY34 Cost: | $247 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | 4232 Approved by FHWA | |
CON | Final ROW Clearance | |
CON | Final Utility Clearance | |
CON | Let | 2018-10-04 |
CON | Award Contract | 2018-11-03 |
CON | Start of Phase | 2018-12-04 |
CON | Notice to Proceed | 2018-11-19 |
CON | Completion of Phase | 2021-12-24 |
CON | Physical Work Complete | 2022-03-20 |
CON | Phase on Approved STIP | |
CON | Project Agreement End Date | 2023-09-16 |