47147 | 3rd Street Dam Over Broomall Lake (Media Borough, Delaware County)
This project involves replacing the Broomall Lake dam carrying 3rd St., which is currently closed to traffic due to the dam's deterioration. The project also includes roadway reconstruction and stormwater management improvements. A final alternative for bridge rehabilitation or replacement is determined upon National Environmental Policy Act (NEPA) clearance.
Limits: Over Broomall Lake/tributary to Ridley Creek
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 183 | $0 | $400 | $0 | $0 | $0 |
FD | LOC | $0 | $100 | $0 | $0 | $0 |
CON | LOC | $0 | $35 | $0 | $0 | $623 |
CON | 183 | $0 | $140 | $0 | $0 | $2492 |
Program Year Totals: | $0 | $675 | $0 | $0 | ||
Total FY23-FY26 Cost: | $675 | Total FY23-FY34 Cost: | $3,790 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Award Contract | 2024-02-21 |
CON | Start of Phase | 2024-03-23 |
CON | Notice to Proceed | 2024-03-23 |
CON | Physical Work Complete | 2025-08-13 |
CON | Let | 2025-09-12 |
CON | Completion of Phase | 2025-09-20 |
CON | Project Agreement End Date | 2027-02-11 |