17678 | Spring Garden over Amtrak (Philadelphia City)

This project will rehabilitate or replace the Spring Garden Street Bridges over rail facilities, north of 30th St. Station..
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.

Limits: over Amtrak
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PE183$1000$1000$1500$0$0
FD183$0$0$0$0$5250
UTLBRIP$0$0$0$0$9500
CONBRIP$0$0$0$0$28274
CON183$0$0$0$0$1426
Program Year Totals:$1,000$1,000$1,500$0 
Total FY23-FY26 Cost:$3,500Total FY23-FY34 Cost:$47,950 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONStart of Phase2022-07-01
FDPhase Approved by PMC
PEPhase Approved by PMC
UTLPhase Approved by PMC
PEPhase on Approved STIP
CONPhase Approved by PMC
PEStart of Phase2023-02-28
PECompletion of Phase2025-10-01
CONCompletion of Phase2027-12-30
FDStart of Phase2028-09-30
UTLStart of Phase2029-09-30
FDCompletion of Phase2030-10-01
UTLCompletion of Phase2032-10-01