17511 | City Ave o/ SEPTA (Bridge) (Philadelphia City & Lower Merion Township)
This project involve rehabilitating or replacing the state bridge over the SEPTA rail line on City Avenue (US 1) between Bala Avenue and Belmont Avenue in the City of Philadelphia. Poor condition bridge breakout project from MPMS #88706. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: over SEPTA Cynwyd Line
Lower Merion
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | NHPP | $400 | $0 | $0 | $0 | $0 |
FD | 185 | $100 | $0 | $0 | $0 | $0 |
ROW | NHPP | $360 | $0 | $0 | $0 | $0 |
ROW | 185 | $90 | $0 | $0 | $0 | $0 |
CON | STU | $3873 | $3873 | $0 | $0 | $0 |
CON | 185 | $968 | $968 | $0 | $0 | $0 |
Program Year Totals: | $5,791 | $4,841 | $0 | $0 | ||
Total FY23-FY26 Cost: | $10,632 | Total FY23-FY34 Cost: | $10,632 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Let | 2023-07-13 |
CON | Award Contract | 2023-08-12 |
CON | Start of Phase | 2023-09-10 |
CON | Notice to Proceed | 2023-09-11 |
CON | Physical Work Complete | 2024-08-22 |
CON | Completion of Phase | 2024-10-21 |
CON | Project Agreement End Date | 2026-02-20 |