❮ Back

17511 | City Ave o/ SEPTA (Bridge) (Philadelphia City & Lower Merion Township)

This project involve rehabilitating or replacing the state bridge over the SEPTA rail line on City Avenue (US 1) between Bala Avenue and Belmont Avenue in the City of Philadelphia. Poor condition bridge breakout project from MPMS #88706. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.

Limits: over SEPTA Cynwyd Line Lower Merion
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FDNHPP$400$0$0$0$0
FD185$100$0$0$0$0
ROWNHPP$360$0$0$0$0
ROW185$90$0$0$0$0
CONSTU$3873$3873$0$0$0
CON185$968$968$0$0$0
Program Year Totals:$5,791$4,841$0$0 
Total FY23-FY26 Cost:$10,632Total FY23-FY34 Cost:$10,632 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONPhase on Approved STIP
CONLet2023-07-13
CONAward Contract2023-08-12
CONStart of Phase2023-09-10
CONNotice to Proceed2023-09-11
CONPhysical Work Complete2024-08-22
CONCompletion of Phase2024-10-21
CONProject Agreement End Date2026-02-20