16334 | PA 73, Church Road Intersection and Signal Improvements (Cheltenham Township, Montgomery County)

This project involves the addition of turn lanes at the PA 73 intersections with Greenwood Avenue and at Rices Mill Road. Left turn lanes will be added on Church Road and right turn lanes will be added on Greenwood Avenue. The traffic signals on PA 73 at Greenwood Avenue and Rice's Mill Road will be interconnected. Drainage in the area will be improved. The existing sidewalk on the east side of Greenwood going north from the intersection with Church Road will be maintained. Additional sidewalks can be considered if there is local support, including the willingness to be responsible for maintenance, and if the improvements can be made ADA compliant. However, the right-of-way constraints are significant, including the Curtis Arboretum and the Rabbinical College. The impacts of additional required right-of-way for bicycle or pedestrian facilities may cause cultural resource and/or community impacts that are not acceptable. These issues will be addressed as the project moves into final design.

Limits: Greenwood Avenue to Rice's Mill Road
Air Quality Code: 2035M

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
ROWTOLL$0$0$0$0$0
ROWCAQ$1938$0$0$0$0
UTLCAQ$278$0$0$0$0
UTLTOLL$0$0$0$0$0
CONTOLL$0$0$0$0$0
CONCAQ$0$11907$0$0$0
Program Year Totals:$2,216$11,907$0$0 
Total FY23-FY26 Cost:$14,123Total FY23-FY34 Cost:$14,123 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
UTLPhase Approved by PMC
ROW4232 Approved by FHWA
UTL4232 Approved by FHWA
ROWStart of Phase2007-12-15
UTLStart of Phase2007-12-15
UTLCash Flow Start2008-10-17
UTLCompletion of Phase
CONPhase Approved by PMC
CONCash Flow Start2016-08-16
CONCash Flow End2017-07-16
ROWPhase Approved by PMC
ROWPlan to ROW Unit2020-06-03
ROWCompletion of Phase2022-09-30
CONPhase on Approved STIP
ROWPhase on Approved STIP
UTLPhase on Approved STIP
UTLPlan to Utility Unit2020-06-03
CONLet2023-09-14
CONAward Contract2023-10-14
CONStart of Phase2023-11-13
CONNotice to Proceed2023-11-13
CONPhysical Work Complete2026-04-09
CONCompletion of Phase2026-06-08
CONProject Agreement End Date2027-10-08