❮ Back

16214 | PA 611, Old York Road Over SEPTA West Trenton Line (Bridge) (Abington Township, Montgomery County)

The Old York Road bridge is a three span, concrete-encased, I-beam structure supported by reinforced concrete abutments and column pier bents and must be replaced with a new structure. This structure carries five travel lanes (including one left turning lane) of PA Route 611 and two pedestrian sidewalks with a total structure width of 69 feet and structure length of approximately 113 feet. Pedestrian access will be provided to both sides of the bridge from the SEPTA Noble regional rail station. Signalized intersections are located at each approach to the bridge. The existing bridge was rated poor in an inspection report performed in 2019. The overall bridge is deteriorating. The abutment has wide cracks, severe scale and large spalls. The superstructure over the loading platforms are exhibiting spalls and heavy scale. There were two small holes noted in the sidewalk on the bridge.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.

Limits: Over SEPTA West Trenton Line (Noble Station)
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FD185$200$0$0$0$0
UTL185$106$0$0$0$0
CONSTU$0$1000$4370$3511$0
CON185$0$250$1092$1934$0
CONBRIP$0$0$0$4229$0
Program Year Totals:$306$1,250$5,462$9,674 
Total FY23-FY26 Cost:$16,692Total FY23-FY34 Cost:$16,692 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
UTLPhase Approved by PMC
CONPhase Approved by PMC
UTLCompletion of Phase2008-04-15
UTLStart of Phase2005-03-15
UTLCash Flow Start
UTLPlan to Utility Unit2010-09-15
UTLCash Flow End2016-02-08
CONFinal ROW Clearance
CONPhase on Approved STIP
UTLPhase on Approved STIP
CONLet2023-06-22
CONStart of Phase2023-06-28
CONAward Contract2023-07-22
CONNotice to Proceed2023-08-21
CONCompletion of Phase2025-09-13
CONPhysical Work Complete2025-10-31
CONProject Agreement End Date2027-05-01