16150 | Tookany Creek Parkway Bridge Over Tookany Creek (Cheltenham Township, Montgomery County)
This project involves rehabilitating or replacing the weight-limit posted Tookany Creek Parkway bridge over the tributary of the Tookany Creek in Cheltenham Township, just east of New 2nd Street (Bridge Bill 2). A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Over Tookany Creek
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
ROW | BOF | $50 | $0 | $0 | $0 | $0 |
ROW | LOC | $3 | $0 | $0 | $0 | $0 |
ROW | 183 | $9 | $0 | $0 | $0 | $0 |
UTL | STP | $55 | $0 | $0 | $0 | $0 |
UTL | LOC | $3 | $0 | $0 | $0 | $0 |
UTL | 183 | $10 | $0 | $0 | $0 | $0 |
CON | 183 | $0 | $369 | $0 | $0 | $0 |
CON | LOC | $0 | $122 | $0 | $0 | $0 |
CON | STP | $0 | $1967 | $0 | $0 | $0 |
Program Year Totals: | $130 | $2,458 | $0 | $0 | ||
Total FY23-FY26 Cost: | $2,588 | Total FY23-FY34 Cost: | $2,588 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
ROW | Start of Phase | |
CON | Phase Approved by PMC | |
UTL | Start of Phase | 2008-01-15 |
CON | Cash Flow Start | 2017-06-15 |
CON | Cash Flow End | 2018-05-15 |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Completion of Phase | 2023-05-15 |
UTL | Plan to Utility Unit | 2024-08-15 |
ROW | Plan to ROW Unit | 2024-08-15 |
CON | Let | 2025-04-10 |
CON | Award Contract | 2025-05-10 |
CON | Start of Phase | 2025-06-09 |
CON | Notice to Proceed | 2025-06-09 |
CON | Physical Work Complete | 2026-11-20 |
CON | Project Agreement End Date | 2028-05-20 |