15278 | Chester Pike/9th Street Bridge over Darby Creek (CB #146) (Collingdale Borough & Darby Borough, Delaware County)
This project involves rehabilitating or replacing the Bridge at Chester Pike/9th Street Bridge over Darby Creek (CB #146).
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | 185 | $0 | $900 | $0 | $0 | $0 |
FD | 185 | $0 | $0 | $0 | $0 | $750 |
ROW | 185 | $0 | $0 | $0 | $0 | $125 |
UTL | 185 | $0 | $0 | $0 | $0 | $150 |
CON | BRIP | $0 | $0 | $0 | $0 | $8000 |
Program Year Totals: | $0 | $900 | $0 | $0 | ||
Total FY23-FY26 Cost: | $900 | Total FY23-FY34 Cost: | $9,925 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Start of Phase | 2022-07-01 |
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
PE | Start of Phase | 2023-01-15 |
FD | Start of Phase | 2024-08-13 |
PE | N. E. P. A. Approval | 2024-08-14 |
PE | Completion of Phase | 2024-09-13 |
CON | Completion of Phase | 2027-12-30 |
ROW | Start of Phase | 2028-09-30 |
FD | Completion of Phase | 2028-09-30 |
UTL | Start of Phase | 2028-10-01 |
UTL | Completion of Phase | 2029-10-01 |
ROW | Completion of Phase | 2030-09-30 |