❮ Back

14698 | US 422, Reconstruction (M2B) (North Coventry Township, Chester County)

Reconstruction of approximately 1.5 miles of expressway including three (3) bridges carrying SR 0422 over Laurelwood Road, SR 0100 (32.8 Sufficiency Rating), and Hanover Street. Acceleration and deceleration lane lengths along US 0422 will be increased to meet current design standards as well as increased shoulder widths will be provided meeting current design standards and US 0422 typical section. SR 0422 will be reconstructed with a 9 foot left shoulder, 2-12 foot lanes, and a 12 foot right shoulder in each direction of travel. A concrete glare screen will be provided for physical separation between eastbound and westbound traffic. Also see MPMS #s 16738, 64220, 64222, 84308, and 66986.

Limits: East of Schuylkill River to East of Hanover Street
Air Quality Code: S10

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FD581$0$1154$0$0$0
FDNHPP$0$4616$0$0$0
ROWNHPP$594$0$0$0$0
ROW581$149$0$0$0$0
UTL581$0$0$113$0$0
UTLNHPP$0$0$450$0$0
CONSPK-NHPP$0$0$36000$20000$0
CON581$0$0$9000$5000$5133
CONNHPP$0$0$0$0$20535
Program Year Totals:$743$5,770$45,563$25,000 
Total FY23-FY26 Cost:$77,076Total FY23-FY34 Cost:$102,744 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
ROWPhase Approved by PMC
ROWStart of Phase2006-02-17
UTLStart of Phase2006-02-17
UTLCompletion of Phase2007-12-15
ROWCompletion of Phase2008-12-15
UTLPhase Approved by PMC
UTL4232 Approved by FHWA
ROW4232 Approved by FHWA
UTLPlan to Utility Unit2022-06-30
ROWPhase on Approved STIP
CONPhase on Approved STIP
UTLPhase on Approved STIP
ROWPlan to ROW Unit2022-12-27
CONStart of Phase2024-06-10
CONLet2025-04-10
CONAward Contract2025-05-10
CONNotice to Proceed2025-06-09
CONCompletion of Phase2026-04-21
CONPhysical Work Complete2028-10-21
CONProject Agreement End Date2030-04-21