14332 | Embreeville O/W Br Brandywine (Chester County)
This project will rehabilitate a bridge.
09/28/2022--Project (paper) let, District control has been changed from Gannett/A. Harper to CONSTR. Low bidder was Loftus Construction Company, with a low bid amount of $1,749,000.
9/22/2021--Description updated. Bridge restoration pursuant to Hurricane Ida.
Limits: Newlin Township
Air Quality Code: X13
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | 185 | $44 | $0 | $0 | $0 | $0 |
CON | FFL | $179 | $0 | $0 | $0 | $0 |
Program Year Totals: | $223 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $223 | Total FY23-FY34 Cost: | $223 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final Utility Clearance | |
CON | 4232 Approved by FHWA | |
CON | Final ROW Clearance | |
CON | Let | 2022-09-29 |
CON | Phase on Approved STIP | |
CON | Notice to Proceed | 2022-10-03 |
CON | Award Contract | 2022-10-29 |
CON | Start of Phase | 2022-11-28 |
CON | Completion of Phase | 2023-03-01 |
CON | Physical Work Complete | 2023-04-01 |
CON | Project Agreement End Date | 2024-06-30 |