❮ Back

14332 | Embreeville O/W Br Brandywine (Chester County)

This project will rehabilitate a bridge.
09/28/2022--Project (paper) let, District control has been changed from Gannett/A. Harper to CONSTR. Low bidder was Loftus Construction Company, with a low bid amount of $1,749,000.
9/22/2021--Description updated. Bridge restoration pursuant to Hurricane Ida.

Limits: Newlin Township
Air Quality Code: X13

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
CON185$44$0$0$0$0
CONFFL$179$0$0$0$0
Program Year Totals:$223$0$0$0 
Total FY23-FY26 Cost:$223Total FY23-FY34 Cost:$223 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONFinal Utility Clearance
CON4232 Approved by FHWA
CONFinal ROW Clearance
CONLet2022-09-29
CONPhase on Approved STIP
CONNotice to Proceed2022-10-03
CONAward Contract2022-10-29
CONStart of Phase2022-11-28
CONCompletion of Phase2023-03-01
CONPhysical Work Complete2023-04-01
CONProject Agreement End Date2024-06-30