❮ Back

13440 | Allentown Road and PA 663 Bridges (2) Over Licking Creek (Milford Township, Bucks County)

The project includes the replacement of 2 bridges: one carrying PA 663 over Unami Creek, and one carrying Allentown Road Bridge over Licking Creek. The replacement of the PA 663 Bridge over Unami Creek will be designed for sufficient width to accommodate staged traffic control during construction of the roadway widening. The structure will also be designed to be able to accommodate structural and hydraulic considerations for future widening to a five-lane section. This project also includes the widening of Allentown Road at the S.R. 0663 intersection to accommodate a two-lane section with a left turn lane on the southbound approach as well as the turning movement requirements for the WB-50 design vehicle with the minimum approach work possible. The northbound approach will be designed for a minimum two-lane section with the possibility of a left turn lane investigated; the replacement of the existing traffic signal equipment at the PA 663 intersection with Allentown Road and revisions to the traffic signal phasing and timing to improve operational inefficiencies, and the reconstruction of the existing pavement within the project limits.
All work on PA 663 and Allentown Road will be reduced in length from the original design to that which is necessary to meet required left turn lane and taper lengths and hydraulic considerations for the Unami Creek Bridge and Licking Creek Bridge. It is anticipated that approximately 2,420 feet of PA 663 and approximately 600 feet of Allentown Road will be reconstructed.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.

Limits: Over Licking Creek
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FD185$150$350$0$0$0
CONBRIP$0$0$0$0$3100
CONSTU$0$699$4000$0$399
CONNHPP$3396$0$0$0$0
Program Year Totals:$3,546$1,049$4,000$0 
Total FY23-FY26 Cost:$8,595Total FY23-FY34 Cost:$12,094 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONCash Flow Start2017-07-06
CONCash Flow End2018-12-06
CONPhase Approved by PMC
CONPhase on Approved STIP
CONLet2024-03-14
CONAward Contract2024-04-13
CONNotice to Proceed2024-05-13
CONStart of Phase2024-05-13
CONPhysical Work Complete2026-07-15
CONCompletion of Phase2026-09-13
CONProject Agreement End Date2028-01-13