12965 | Lawn Avenue (Sellersville Borough & West Rockhill Township, Bucks County)

Reconstruct roadway, curbs, sidewalks, and walls. Construct new sidewalk and curbs in areas currently without them. Perform a minor relocation of one horizontal curve. Install new drainage facilities as required. Relocate affected water and sanitary sewer lines as required. A portion of the roadway from Noble St to Maple Ave is proposed to be turned back to the borough upon completion of the project. Upon completion of the project sidewalk will be in place from Grandview Hospital to the borough center.

Limits: Maple Avenue to Farmers Lane
Air Quality Code: S10

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FD581$86$0$0$0$0
FDSTU$344$0$0$0$0
UTLSTU$0$0$0$1869$0
UTL581$0$0$0$467$0
CONSTU$0$0$0$376$0
CON581$0$0$0$94$0
Program Year Totals:$430$0$0$2,806 
Total FY23-FY26 Cost:$3,236Total FY23-FY34 Cost:$3,236 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
FDPhase Approved by PMC
UTLPhase Approved by PMC
UTLStart of Phase2003-11-15
CONCash Flow Start2013-05-15
CONCash Flow End2014-07-15
UTLCompletion of Phase2017-10-16
FDCompletion of Phase2020-02-14
UTLPhase on Approved STIP
FDPhase on Approved STIP
CONPhase on Approved STIP
FDStart of Phase2024-02-16
UTLPlan to Utility Unit2024-06-19
FDPS+E to District Contract Management2025-08-20
CONLet2026-04-09
CONAward Contract2026-05-09
CONNotice to Proceed2026-06-08
CONStart of Phase2026-06-08
CONPhysical Work Complete2027-10-29
CONCompletion of Phase2027-12-28
CONProject Agreement End Date2029-04-28